Confidential Customer: U.S. IPP
Year Completed: Ongoing
Project: Recommend equipment modifications and assist with overall vendor selection for a poultry litter-fuel fired electricity generation plant ilocated in North Carolina.
Confidential Client: U.S. IPP
Year Completed: Ongoing
Develop methodology to capture remaining heat from steam used in Steam Coil Air Heaters and return energy to the system via use of a cyclonic separator and pumps.
Confidential Client: Greenhouse Facility
Year Completed: 2022
Co-developed a test plan and witnessed a used generator load bank test for a client in rural Mississippi procuring a used diesel generator for their start-up business.
Confidential Client: U.S. IPP
Year Completed: 2022
Developed concept and worked closely with the plant conveyor OEM to install conveyors to eliminate bottlenecking around obsolete wood dryers at two biomass stations.
Confidential Client: U.S. IPP
Year Completed: 2022
Performed sizing, developed concept, selected vendors, and managed turnkey installation of Steam Coil Air Heaters (SCAH) for two biomass plants to eliminate cold-end corrosion.
Confidential Client: U.S. IPP
Year Completed: 2021
Project: Investigate the suitability for reuse of an existing shuttered CFB for independent inside-the-fence power at a sand mine.
Confidential Client: U.S. IPP
Year Completed: 2021
Project: Review components in storage and assess feasibility of reuse for project located in Ohio, USA.
Confidential Customer: Irish Engineering Firm
Year Completed: 2020
Project: Travel to a remote site outside of Fortaleza, Brazil to assess the feasibility of using landfill gas (biogas) in a new facility boiler.
Confidential Customer: U.S. AE Firm
Year Completed: 2020
Project: Review extent of shop work completed and ascertain readiness to ship for six (6) biomass-fired boilers being built in Georgia for installation in southern Africa.
Confidential Customer: U.S. AE Firm
Year Completed: 2019
Project: Performed a site investigation and equipment assessment for a client leading the due diligence of the potential purchase of a mothballed generation facility in S. Georgia.
Confidential Customer: U.S. IPP
Year Completed: 2019
Project: Collection of data from plant DCS and investigation of a boiler perfromance output, made recommendations for modifications of 2 biomass-fired boilers located in Georgia.
Confidential Customer: U.S. IPP
Year Completed: 2019
Project: Performed an equipment inspection, detailed report, and investigation of similar designs to make a recommendation for modification of a biomass-fired boiler in GA.
Confidential Customer: U.S. IPP
Year Completed: 2019
Project: When boiler performance deficiencies resulted in a vendor's claims of non-spec fuel, we analyzed various fuel samples using both in-house and external testing sources.
Confidential Customer: U.S. Developer
Year Completed: 2012
Project: Detailed project financing model including project CAPEX and OPEX vis-a-vis predicted project revenue for Year 1 and Year 20 of a biomass-fired facility in Virginia.
Confidential Customer: Italian Boiler Supplier
Year Completed: 2011
Project: Detailed a list of suppliers (including price levels) of American-made equipment for an Italian Boiler supplier contemplating entering the US market with their product.
Copyright © 2021 American Power Consultants LLC - All Rights Reserved.
Powered by GoDaddy
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.